This shows (top picture) the six rivets on each side of the seat "V" area that get replaced with 6 new bolts. Six bolts on each side of the aircraft going lengthwise along the fuselage in the seat "V" area to strengthen the main landing gear frame.

 

The bottom pic shows the six bolts going perpendicular to the fuselage, with the bolt heads now on the inside of the fuselage and the nuts on the outside. These six bolts on each side of the aircraft had to be removed early on in the service bulletin to gain access to the six rivets that had to be drilled out on each side. The picture shows 6 new bolts now going back in, perpendicular to the fuselage, completing the service bulletin main landing gear fasteners.


From the album:

PiperSportDK

· 70 images
  • 70 images
  • 0 comments
  • 1 image comment


Recommended Comments

There are no comments to display.

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Add a comment...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...